  1. Pre-requisites: 
    a. Selectthe applicable forms from the Pipeline Task list. 
    b. Complete Section A.
  2. Select the H tab at the top of the dialog box. 
    The Abandoned Idled - Section H dialog displays. 
    Use the right-side scroll bar to view and access all of the fields and check boxes. 
    RTENOTITLE
  3. Complete the H tab by completing each field as required or necessary:

 

Section H Fields

Field Action
Upstream GPS Not yet available
Downstream GPS Not yet available
Was Pipe Purged with Nitrogen? Select either the Yes or No radio button.
Was Pipeline Cut and Capped? Select either the Yes or No radio button.
Portion of Pipe Cut Still in Service? Select either the Yes or No radio button.
Is This Under a Navigable Waterway? Select either the Yes or No radio button.
  1. When you are done filling out Section H, click Save.
  2. Click Yes at the confirmation prompt.
  3. Click OK at the confirmation prompt.
  4. Complete any additional sections that are required for the form you are creating.
  5. Complete the Status section.